新聞中心
直線(xiàn)導(dǎo)軌的幾種安裝方法
來(lái)源:http://www.idczc.com/ 日期:2023-02-28 發(fā)布人:
隨著高精密的直線(xiàn)導(dǎo)軌在工業(yè)自動(dòng)化中運(yùn)用的廣泛性,掌握一定的安裝技巧是很有必要的,正確的安裝方法能提高導(dǎo)軌的使用壽命與使用精度。下面導(dǎo)軌絲杠廠家為您分析:
With the wide application of high-precision linear guide rail in industrial automation, it is necessary to master certain installation skills. The correct installation method can improve the service life and accuracy of the guide rail. The following guide screw manufacturer will analyze for you:
一、使用安裝基準(zhǔn)面安裝方法
1、 Installation method using installation reference plane
先使用裝配螺絲將直線(xiàn)導(dǎo)軌底部基準(zhǔn)面大概固定于床臺(tái)底部裝配面,再用虎鉗將滑軌側(cè)邊基準(zhǔn)面逼緊床臺(tái)側(cè)邊裝配面,以確定滑軌位置后,使用扭力扳手,一定的扭力按順序鎖緊固定螺絲,將滑軌底部基準(zhǔn)面逼緊床臺(tái)底部裝配面。
First, use the assembly screws to fix the bottom datum plane of the linear guide rail to the assembly surface at the bottom of the bed, and then use the vice to press the side datum plane of the slide rail against the assembly surface at the side of the bed, so as to determine the position of the slide rail, then use the torque wrench to lock the fixed screws in sequence with a certain amount of torque, and press the bottom datum plane of the slide rail against the assembly surface at the bottom of the bed.
二、從動(dòng)側(cè)直線(xiàn)導(dǎo)軌的安裝
2、 Installation of linear guide rail on the driven side
1、直線(xiàn)塊規(guī)法
1. Straight block gauge method
將直線(xiàn)塊規(guī)置于兩支直線(xiàn)導(dǎo)軌間,使用千分量表校準(zhǔn)直線(xiàn)塊規(guī),使之與基準(zhǔn)側(cè)滑軌之側(cè)邊基準(zhǔn)面平行,再依直線(xiàn)塊規(guī)校準(zhǔn)從動(dòng)側(cè)滑軌,從動(dòng)軌的一端開(kāi)始校準(zhǔn)并依序以特定的扭力鎖緊裝配螺絲。
Place the linear block gauge between the two linear guides, calibrate the linear block gauge with a micrometer to make it parallel to the side reference plane of the reference side slide rail, and then calibrate the driven side slide rail according to the linear block gauge. Start to calibrate one end of the driven rail and lock the assembly screws with a specific torque in sequence.


2、移動(dòng)平臺(tái)法
2. Mobile platform method
將基準(zhǔn)側(cè)兩個(gè)滑塊固定在一個(gè)測(cè)定平臺(tái)上,而從動(dòng)側(cè)只裝上一個(gè)滑塊,滑軌和滑塊都尚未固定于床臺(tái)與平臺(tái),使用附于從動(dòng)側(cè)滑塊頂面千分量表,量測(cè)從動(dòng)側(cè)滑塊的側(cè)基準(zhǔn)面,從動(dòng)直線(xiàn)導(dǎo)軌的一端開(kāi)始校準(zhǔn)并依序以特定的扭力鎖緊裝配螺絲。
Fix the two sliders on the reference side on a measuring platform, while the driven side is only equipped with one slider. The sliders and sliders have not been fixed on the bed and platform. Use the dial indicator attached to the top surface of the sliders on the driven side to measure the side reference plane of the sliders on the driven side. Start to calibrate one end of the driven linear guide rail and lock the assembly screws with a specific torque in sequence.
3、效仿基準(zhǔn)側(cè)滑軌法
3. Follow the reference side slide rail method
將基準(zhǔn)側(cè)直線(xiàn)導(dǎo)軌的兩個(gè)滑塊及從動(dòng)側(cè)導(dǎo)軌其中一個(gè)滑塊固定于平臺(tái),再將從動(dòng)側(cè)的滑軌及其另一個(gè)滑軌約略分別固定于床臺(tái)及平臺(tái),以基準(zhǔn)側(cè)滑軌為準(zhǔn)移動(dòng)平臺(tái),從滑軌一端開(kāi)始,邊確認(rèn)從動(dòng)側(cè)直線(xiàn)導(dǎo)軌的滾動(dòng)阻力,邊依序以特定的扭力鎖緊裝配螺絲。
Fix the two sliders of the linear guide rail on the reference side and one of the sliders on the driven side on the platform, and then roughly fix the slide rail on the driven side and the other slide rail on the bed and platform respectively. Move the platform based on the reference side slide rail. From one end of the slide rail, confirm the rolling resistance of the linear guide rail on the driven side, and lock the assembly screws with a specific torque in sequence.
4、專(zhuān)用工具法
4. Special tool method
使用工具確定從動(dòng)側(cè)滑軌的位置,并依序以特定的扭力鎖緊裝配螺絲。
Use professional tools to determine the position of the slide rail on the driven side and lock the assembly screws with specific torque in sequence.
直線(xiàn)導(dǎo)軌的幾種安裝方法講解完畢了,希望給您好的幫助吧!有疑惑或者有需求可以隨時(shí)來(lái)我們網(wǎng)站http://www.idczc.com留言咨詢(xún)!
Several installation methods of linear guide rail have been explained. I hope to give you good help! Come to our website at any time if you have doubts or need http://www.idczc.com Message consultation!